T.N. may see solar energy installations slowing down, say energy generators
Tamil Nadu, which has 10,000 MW-11,000 MW of installed solar energy capacity, may see a slowdown in solar energy installations in 2027, according to industry representatives.
The single window system for obtaining approvals is not functioning effectively, finer details based on the recently-announced Battery Energy Storage System (BESS) Policy should be notified by the Tamil Nadu Electricity Regulatory Commission, and costs are escalating, say solar energy investors.
“No approvals have been granted for solar energy projects for almost six months now. Only now has the government started accepting the applications. Even if they are approved now, it is difficult to commission the projects by March 2027. From April next year, it is mandatory for all new projects to have BESS, and this will push the costs up,” said one of the solar energy investors in Coimbatore.
“We had a detailed discussion with the TNERC on the BESS policy. The policy says there will be waiver of wheeling charges. The wheeling charges are applicable only if a consumer buys under open access. However, the policy says solar energy generators who store energy can sell it only to the State utility. There are many such issues with the policy that need better clarity in the policy,” says AD Thirumoorthy, State Level Renewable Energy Committee Member, Government of Tamil Nadu.
The single window approval system is functioning effectively for solar energy projects that come as a part of foreign direct investments. The others require multiple approvals, starting right from the rural local body heads. These lead to delays, pushing up the costs, he added.
While the BESS policy is a welcome move, the Tamil Nadu Green Energy Corporation should ensure that stored solar energy is evacuated within 24 hours, so that the generator can store freshly generated energy the next day, said L. Santhosh, president of the Tamil Nadu Electricity Consumers Association.
In the last one month, some of the solar energy generators received notices demanding 8% banking charges. These are not applicable because the court has stayed the green energy open access policy of the State, he added. More sub-stations and solutions for right of way challenges to lay lines on lands belonging to various government departments are among the other issues faced by investors that threaten to slow down solar energy projects.