The Tema Oil Refinery (TOR) is working to increase its crude-processing rate from approximately 28,000 barrels per stream day to between 45,000 and 55,000 barrels per stream day, Managing Director Edmond Kombat has announced. Speaking at the Government Accountability Series at Jubilee House on Monday, October 26, 2026, Mr Kombat said the work was expected to improve the performance of the Crude Distillation Unit (CDU) and move the plant towards its nameplate capacity.

The Tema Oil Refinery (TOR) is working to increase its crude-processing rate from approximately 28,000 barrels per stream day to between 45,000 and 55,000 barrels per stream day, Managing Director Edmond Kombat has announced.

He said engineers from Verga Engineering were working alongside TOR’s technical team to complete the tie-in and commission the F-61 crude heater, a critical component in the refinery’s ongoing operational recovery.

Speaking at the Government Accountability Series at Jubilee House on Monday, October 26, 2026, Mr Kombat said the work was expected to improve the performance of the Crude Distillation Unit (CDU) and move the plant towards its nameplate capacity.

“Engineers from Verga Engineering are currently on site, working on with TOR’s technical team to increase the throughput to between 45,000bpsd to 55,000bpsd,” he said.

The CDU was refurbished under a turnaround maintenance programme conducted between August 1 and October 30, 2025. Crude processing resumed on December 19, 2025, after the National Petroleum Authority inspected the plant and cleared it for operations.

President John Dramani Mahama subsequently commissioned the refurbished unit on August 1, 2026.

Mr Kombat said management had prioritised the CDU’s rehabilitation after inheriting a refinery whose major processing units had remained inactive for several years.

The CDU had been out of operation since April 2021, while the Residue Fluid Catalytic Cracking (RFCC) unit had been shut down since 2019.

He said the turnaround maintenance was funded entirely from TOR’s internally generated funds and carried out by the refinery’s engineers and technicians.

“Work also resumed on critical stalled projects, including Boiler No. 8, the F-61 Crude Heater, the Residue Air Cooler and the Steam Turbine Generator,” he said.

Management is also planning to install a new air cooler to increase processing capacity to 60,000 barrels per stream day and replace the existing 6,500-barrel-a-day catalytic reformers with a 10,000-barrel-per-day continuous catalytic reformer.

Mr Kombat said a new 120-tonne boiler had been installed, while work continued on the RFCC turnaround and the SCADA system.

Beyond the immediate engineering interventions, the government has directed TOR’s board and management to develop a roadmap for increasing processing capacity to 100,000 barrels per day, with a longer-term ambition of reaching 200,000 barrels per day.

Mr Kombat said the proposed improvements were intended to strengthen refining capacity, improve operational reliability and increase the refinery’s contribution to domestic petroleum supply.

He acknowledged that the recovery process was ongoing, adding that management remained focused on completing outstanding engineering works and sustaining the gains made since operations resumed.

  • tor
  • work
  • barrel
  • stream
  • crude
  • heater
  • refinery
  • processing

Summaries and tags are generated automatically. Stay informed with VidiaNews.

Related news

Mahama to open GH¢148.4m cashew processing factory in Techiman – Kwakye Ofosu
technology

Mahama to open GH¢148.4m cashew processing factory in Techiman – Kwakye Ofosu

President John Dramani Mahama is expected to travel to Techiman on Monday to officially open the Nadkansco Cashew Processing Factory, a GH¢148.4 million facility financed by the Ghana Export-Import Bank (GEXIM). The announcement was made by the Minister in charge of Government Communications, Felix Kwakye Ofosu, in a Facebook post, highlighting the facility’s potential to create jobs, strengthen local cashew processing and support farmers.

Read →
Guardian to follow lives of eight young people in their search for work
business

Guardian to follow lives of eight young people in their search for work

Series to shine light on one of biggest crises facing UK ‘The social contract is broken’: young people on feeling shut out of careers Britain is at risk of creating a lost generation. Before the landmark Alan Milburn review, which is expected on Tuesday, the Guardian is launching a new series to chronicle the lives of eight young people battling to get a start on the career ladder.

Read →
Gideon Boako accuses Mahama of recycling $10bn promises from STX to New Economy Programme
business

Gideon Boako accuses Mahama of recycling $10bn promises from STX to New Economy Programme

Tano North MP Dr Gideon Boako has accused President John Dramani Mahama of repeatedly announcing ambitious US$10 billion projects without delivering on previous commitments. He made the accusation in a write-up issued on Sunday, November 15, in which he cited the STX housing deal, Hope City, the NDC’s Big Push infrastructure programme and the recently announced New Economy Programme as examples of what he described as a pattern of recycling the same financial commitment under different project names.

Read →
NNPC Receives C-Of-O For Proposed Edo Refinery
business

NNPC Receives C-Of-O For Proposed Edo Refinery

The Nigerian National Petroleum Company Limited (NNPC Ltd.) has received a Certificate of Occupancy (C-of-O) for its proposed Oredo Refinery and Petrochemical Company Limited in Edo State. The Executive Vice President, Downstream, NNPC Ltd., Alhaji Mumuni Dagazau, received the certificate on behalf of the company during a courtesy visit to the Edo State Government House in Benin City on Friday.

Read →