Pampa road upgrade model to be replicated across Keralam

The 4.5-km Pampa–Chalakkayam road was recently upgraded by the PWD in just 30 days, well ahead of the stipulated nine-month deadline
According to PWD Minister P.K. Basheer, the project demonstrated that conventional, time-consuming construction procedures could be replaced through efficient planning, administrative coordination and the involvement of capable contractors
The Public Works department (PWD) has decided to fast-track key road infrastructure and city junction development projects across the State, adopting the Pampa–Chalakkayam road upgrade as a model for time-bound execution. The 4.5-km stretch was recently upgraded by the PWD in just 30 days, well ahead of the stipulated nine-month deadline.
A committee is expected to submit a report to the State government soon, identifying projects to be taken up on a priority basis. The Chalakkayam–Pampa stretch of the Mannarakulanji–Pampa road, a key route for Sabarimala pilgrims, was upgraded to modern standards ahead of the annual pilgrimage. The PWD is showcasing the project as a model for executing major infrastructure works within strict deadlines.
According to PWD Minister P.K. Basheer, the project demonstrated that conventional, time-consuming construction procedures could be replaced through efficient planning, administrative coordination and the involvement of capable contractors. The government would encourage contractors with the capacity to complete major works within stipulated deadlines and replicate the model in other public infrastructure projects, he said.
The road has been widened to 12 metres and equipped with modern safety features, including signboards, crash barriers and road markings. Additional safety measures have been introduced at sharp curves and accident-prone locations, while concrete interlocking blocks have been laid along both sides of the road.
The construction was carried out simultaneously by two teams working from opposite ends. Despite challenges such as bitumen shortages, delays in material availability, adverse weather and traffic restrictions, the work was completed within 30 days. Additional personnel were deployed from neighbouring divisions to complete the work, along with the teams from the PWD’s Pathanamthitta Division, Ranni Sub-Division and Laha Section.
Meanwhile, the PWD is preparing a comprehensive package for the development of major junctions, bypasses and flyovers across the State. The projects will be taken up in phases based on priorities identified in a study report to be submitted by a committee chaired by Shajahan, IAS. The Pampa–Chalakkayam project would serve as a template for executing the proposed works, demonstrating the department’s capacity to complete major infrastructure projects within stipulated timelines, the Minister said.