The Federal Government is seeking reduction in the period for construction of the new Carter Bridge. The Minister of Works, Sen. Dave Umahi, told the contractor handling the project, China Civil Engineering Construction Corporation (CCECC), to look at the possibility of reducing the time frame from 36 months to 18 months or 24 months.

The Federal Government is seeking reduction in the period for construction of the new Carter Bridge. The Minister of Works, Sen. Dave Umahi, told the contractor handling the project, China Civil Engineering Construction Corporation (CCECC), to look at the possibility of reducing the time frame from 36 months to 18 months or 24 months. He said that the aim was to save more money and ensure that the new Carter Bridge would come on board before the existing one would go down.

He said that CCECC had completed five per cent of the 1.9km bridge project without being paid any mobilisation fee. “No mobilisation fee has been paid to them, and the duration of this project is 36 months but I am striking a deal with their management, having seen that they have gone up to five per cent. “We are going to release, within this week, 30 per cent mobilisation fee to CCECC.

“Another deal will probably be if we can reduce the construction period to about 18 months to 24 months; then, they can apply for loan so they can set up two other sections of piling. ” if they will do that, we are ready to give them a loan of 20 per cent so that they can set up, but they must give us APG – Advance Payment Guarantee,” the minister said.

According to him, the Federal Government already has the APG for the 30 per cent mobilisation fee. “We are not allowed to pay more than 30 per cent but we can give a loan based on an agreement.” He emphasised that the bridge’s piling must be on a minimum of Schedule 60 thick steel pile. He said that the CCECC was meeting the specification. “We are very happy about that.

We also directed that when they start their piling, we have to do a number of big lumps to protect the piles at the seabed,” Umahi said

  • month
  • bridge
  • period
  • carter
  • cent
  • ccecc
  • mobilisation
  • fee

Summaries and tags are generated automatically. Stay informed with VidiaNews.

Related news

FG assures of December completion of Eko Bridge repair
politics

FG assures of December completion of Eko Bridge repair

Repair of the underwater element of Eko Bridge in Lagos, damaged by illegal sand mining, would be completed by December, the Minister of Works, Sen. Dave Umahi, has said. Umahi said that the Federal Government engaged Buildwell Construction Company on emergency work on the bridge.

Read →
‘Monies Borrowed Are Being Used For Investments, Infrastructure’, Umahi Inspects Coastal Road Bridges
politics

‘Monies Borrowed Are Being Used For Investments, Infrastructure’, Umahi Inspects Coastal Road Bridges

The Minister for Works and Infrastructure, David Umahi, has defended the external borrowings of President Bola Tinubu, saying the monies are being invested in the building of infrastructure across the country. This is as President Tinubu has asked the House of Representatives to authorise FG to access $7.71bn (N10.79 trillion) in external loans already captured in the 2026 Appropriation Act, with Eurobond issuance expected to be a major funding option.

Read →
[PHOTOS] FG Targets December For Reopening Of Eko, Iddo Bridges
politics

[PHOTOS] FG Targets December For Reopening Of Eko, Iddo Bridges

The Federal Government has assured Lagos residents that the Eko and Iddo bridges will be fully functional by December 2026, as rehabilitation and reconstruction works continue on the two critical transport links. This image shows ongoing reconstruction of the Iddo Bridge in Lagos. (

Read →
FG disappointed as COP31 ends without political deal
science

FG disappointed as COP31 ends without political deal

The Federal Government has expressed disappointment over the failure of the 31st United Nations Climate Change Conference (COP31) to reach consensus on an overarching political agreement, describing the outcome as a setback for international climate cooperation. The Director-General of the National Council on Climate Change (NCCC), Dr Omotenioye Majekodunmi, said, however, that the development would not weaken Nigeria’s commitment to addressing climate change.

Read →
Abure-led Labour Party faction backs Tinubu for 2027
politics

Abure-led Labour Party faction backs Tinubu for 2027

By John Alechenu, Abuja A faction of the Labour Party (LP) led by Julius Abure has endorsed President Bola Tinubu for re-election in the 2027 general election, pledging to mobilise the six million votes the party claimed in the 2023 polls in support of the President. Abure compared Tinubu’s experience with that of Peter Obi, arguing that the former Labour Party presidential candidate had failed to consolidate the political opportunity he gained after the 2023 general election.

Read →