Semi-high-speed rail project to cost less than additional railway tracks: Sreedharan

Semi-high-speed rail project to cost less than additional railway tracks: Sreedharan

Technocrat E. Sreedharan says the project will require less funding than what the Railways will need to construct the third and fourth tracks parallel to the existing rail corridor

Technocrat and former DMRC Principal Advisor E. Sreedharan delivers a lecture on ‘High-speed rail for Keralam’ in the city on Monday.

While stating that the government was yet to formally respond to an interim report on the Thiruvananthapuram-Kannur semi-high-speed rail corridor that he submitted in May, technocrat E. Sreedharan said the project would require less funding than what the Railways would need to construct the third and fourth tracks parallel to the existing rail corridor.

This is because land acquisition would be minimal for the 472-km semi-high-speed project, which has been envisaged as an elevated corridor. Moreover, the project, estimated to cost approximately ₹60,000 crore, would be powered entirely by solar panels installed on either side of the elevated viaduct. This, in turn, would reduce operation and maintenance expenses by a third, as expenditure would be limited to maintenance and salaries once the project was commissioned.

Reliance on standard-gauge tracks would also help build a sleeker viaduct designed to support a 15-tonne axle load, compared with the 25-tonne axle load of broad-gauge tracks, Mr. Sreedharan, who retired as Principal Advisor of the Delhi Metro Rail Corporation (DMRC), said. He was speaking to media persons after delivering a lecture on ‘High-speed rail for Keralam’, organised by the Kochi centre of the Institution of Engineers (India).

As for funding, he said the State and the Centre could share 60% of the capital expenditure, while the remaining 40% could be raised through crowdfunding. With a fare of ₹800 for the entire Thiruvananthapuram-Kannur journey, approximately 30% of the one lakh rail passengers would shift to the semi-high-speed trains, he said. This would be in addition to passengers shifting from road transport to rail, as the entire journey could be completed in three hours and 30 minutes.

The semi-high-speed project, with a design speed of 200 kmph and a commercial (average) speed of 135 kmph, would have the advantage of having stations every 25 km in densely populated Keralam. In comparison, stations on a high-speed rail system with a design speed of 350 kmph would be located 40 to 50 km apart.

Twelve-coach trains operating every 30 minutes could run at intervals of five minutes, depending on demand. The project had the potential to change the face of Keralam, with productivity doubling in another 10 years, he said.

The project would benefit Ernakulam the most, as there would be four stations in the district, including one near the international airport, Mr. Sreedharan added.