Bengaluru’s Blue Line trials begin from K.R. Puram; public operations targeted for mid-2027, says Minister

Bengaluru’s Blue Line trials begin from K.R. Puram; public operations targeted for mid-2027, says Minister

Trial runs cover the first four stations on the 19-km K.R. Puram-Central Silk Board stretch, with testing to be extended next month; the entire 58.2-km corridor to the airport is targeted for completion within 18 months.

The 19-km Phase 2A section comprises 13 stations and is expected to provide metro connectivity along the ORR, offering relief to thousands of employees commuting to the city’s major technology and business hubs.

Trial runs on the much-awaited Bengaluru Metro Blue Line have commenced from K.R. Puram across the first four stations, with testing scheduled to be extended by another four stations next month.

Public operations on the 19-km Phase 2A corridor connecting K.R. Puram and Central Silk Board are targeted for the middle of 2027, according to Greater Bengaluru Development Minister Krishna Byre Gowda.

Read | Mind the gap: Partial opening of Namma Metro Pink Line leaves commuters wanting

Inspecting the trial runs at Doddanekkundi Metro Station on Tuesday (November 24), the Minister said that the testing would be progressively extended to cover the remaining stations.

“The installation of the automatic signalling system is expected to be completed over the next two to three months, followed by mandatory safety certification. The government is targeting completion of signalling installation by January, with the safety certification process expected to begin after February. Considering the testing and certification requirements, the entire process is likely to take another seven to eight months before the corridor is opened for public use,” Mr. Gowda said.

The 19-km Phase 2A section comprises 13 stations and is expected to provide metro connectivity along the heavily congested Outer Ring Road (ORR), offering relief to thousands of employees commuting to the city’s major technology and business hubs.

Read | Blue Line to open in phases from mid-2027; full stretch by March 2028, says KBG

Mr. Gowda said that an estimated 11-12 lakh people work along the ORR stretch, making it one of Bengaluru’s most important employment and mobility corridors. The metro connectivity is expected to provide a long-term solution to traffic congestion and improve connectivity for daily commuters.

The Minister also said that the government was working to expedite construction under Phase 2B, particularly along the K.R. Puram-Hebbal stretch, where progress needs to be strengthened. Officials have been directed to coordinate with contractors and accelerate the execution of pending works.

The entire 58.2-km Blue Line, connecting Central Silk Board through K.R. Puram and Hebbal to Kempegowda International Airport, is being implemented at an estimated cost of around ₹20,000 crore. The government has set a target of completing the entire corridor within the next 18 months.

Addressing concerns over project funding, Mr. Gowda said the State government was making provisions and releasing funds to ensure that financial constraints did not delay Metro expansion works. He pointed out that fluctuations in foreign exchange rates had increased the loan repayment burden, while delays in approvals had also contributed to rising construction costs.

On the proposed Red Line Metro expansion, the Minister said that discussions had been held with the Union Government, but final approval was still awaited. The State had also proposed a double-decker corridor combining Metro and road infrastructure from Sarjapur through Ibbalur Junction to St. John’s.

As reported earlier by The Hindu, the Ministry of Housing and Urban Affairs (MoHUA) told Parliament in August that the project was under detailed scrutiny, with its approval subject to the outcome of the feasibility assessment and the availability of funds.

Meanwhile, Mr. Gowda also said that the government was examining measures to improve the financial sustainability of Bangalore Metro Rail Corporation Limited (BMRCL).

“The government is also examining ways to strengthen the metro corporation’s revenue streams and improve its financial self-sufficiency. At present, ticket revenue is not sufficient to meet the corporation’s full operating costs. The corporation currently records an annual loss of around ₹600 crore to ₹700 crore, including depreciation, while reporting an operating surplus of ₹50 crore to ₹60 crore when depreciation is excluded,” he said.

However, he clarified that no decision had been taken on increasing metro fares.