Power deal with VEH Global India an ‘exceptional and limited-period contingency measure,’ says KSEB

No RPO benefit for KSEB in deal, shows documents submitted before the Kerala State Electricity Regulatory Commission
The power purchase agreement with VEH Global India Pvt Ltd was undertaken as an “exceptional and limited-period contingency measure and not as a regular arrangement,” the Kerala State Electricity Board (KSEB) has told the Kerala State Electricity Regulatory Commission (KSERC).
The commission has finally admitted a KSEB petition on the agreement, which had kicked up a political storm in Keralam, along with replies to 17 queries posed by the commission. The commission headed by T.K. Jose will take up the petition for a hearing on December 16.
The controversy was linked to the decision to purchase 200 MW for six hours every day during the evenings from September 23 to October 31, 2026. The Opposition Left Democratic Front (LDF) had alleged that the deal would result in a heavy financial loss to the State as wind power cost below ₹4 per unit.
According to the KSEB, the maximum energy charge for 39 days would have come to 46.80 million units and the energy charge for it, ₹51.48 crore. The excess charge on account of purchasing above the ceiling limit would be ₹4.68 crore, according to it.
On the rationale of purchasing electricity at ₹11 per unit while the ceiling rate was ₹10 as set by the commission, the KSEB observed that the “the circumstances necessitating procurement, the availability of alternative sources, the urgency of supply, the period and time blocks of procurement and the consequences of non-availability of power are equally relevant considerations” in an emergency.
At the same time, documents show that in purchasing electricity from VEH Global India Pvt Ltd, the KSEB had decided to forgo renewable purchase obligation (RPO) benefits.
The KSEB has informed the commission about this in replies given to the latter’s queries. The commission had sought the reasons for not availing RPO benefit for the wind power purchased under the agreement. “The power purchase agreement describes the supply as ‘wind-based brown power’ without environmental attributes. The KSEB has sought no RPO credit for this purchase in the petition,” the KSEB has replied.The petition to the commission described the offer as ‘wind-based infirm power.’ The power purchase agreement that the KSEB signed with VEH Global on September 23 said it was for “up to 200 MW of brown power (without any environmental attributes) on a bilateral basis.”
RPO is a requirement specified under Section 86(1)(e) of the Electricity Act, 2003. It requires entities such as distribution companies to source a certain percentage of their total electricity consumption from renewable energy sources.