Pallivasal Extension Scheme cost touched ₹632.5 crore following delays, says Kerala State Electricity Board

Pallivasal Extension Scheme cost touched ₹632.5 crore following delays, says Kerala State Electricity Board

60-MW hydropower project took more than 20 years to complete. The project was originally given administrative sanction for ₹175.86 crore in 2001

The 60-MW Pallivasal Extension Scheme, a hydropower project of the Kerala State Electricity Board (KSEB) took more than 20 years to complete.

The 60-MW Pallivasal Extension Scheme, a hydropower project of the Kerala State Electricity Board (KSEB) that took more than 20 years to complete, has eventually cost a whopping ₹632.59 crore, according to the power utility’s documents.

Originally given administrative sanction in 2001 for ₹175.86 crore, the project was awarded to the ESSAR-DEC-CPPL Consortium in 2006 for ₹268.01 crore. After technical and contractual hiccups, this contract was terminated in 2018. Thereafter, the balance works were executed in separate packages. The then Chief Minister Pinarayi Vijayan inaugurated the scheme, which adds 60 MW/153.9 mu to Keralam’s power grid, in March 2026.

Now, through a November 24, 2026 order, the KSEB has issued a ‘formal revised administrative sanction’ for ₹632.59 crore following a direction by the Kerala State Electricity Regulatory Commission while examining a petition on the capital investment plan of the Pallivasal Extension Scheme. “The Chief Engineer (Project Execution and Buildings) South as per note read as 9th above (dated July 2026), has reported that the total cost of completion, inclusive of miscellaneous works, interest and finance charges, employee cost and administrative and general expenses, is reported as ₹6,32,59,04,249,” reads the November 24 KSEB order.

The KSEB further notes that a ‘consolidated revised administrative sanction’ was not accorded, given the uncertainty regarding the project’s completion. Instead “piece-meal sanction” for balance works were issued on different occasions.

In October 2026, the board of full-time directors of the KSEB examined the factors contributing to the delay. It has now been decided to carry out an independent study through an external expert agency or a committee, for examining and recommending improvements to project management practices.

The Pallivasal Extension Scheme was conceived for meeting the steadily increasing power demand. It was designed as an extension to the 37.5-MW Pallivasal Hydroelectric Project, Kerala’s first hydro project which was commissioned in 1940. The work on the project was awarded to ESSAR-DEC-CPPL Consortium on September 18, 2006, and the agreement was executed on January 31, 2007. As per the original schedule, the work was to have been completed on March 1, 2011. After this contract was terminated in 2018, a new contractor was hired to complete the installation of machinery, but the delays persisted.

In February 2026, the KSEB management had decided not to take action against its officials for the delays that affected this hydel project. The power utility decided to accept a report of its Vigilance wing in this regard which concluded that it would be “undesirable” to initiate action against the officials. “Though the lapse from the officials has caused the delay in the commissioning of the project, the inquiry has not found any evidence for malicious, wilful intent or vested interest,” the KSEB Vigilance wing had noted.