Tension at Nagarjunasagar as A.P. releases water to right canal unilaterally
Telangana engineers oppose water release by AP; After AP’s refusal to stop release, Telangana starts releasing water to left canal
Tension prevailed on Nagarjunasagar dam on Thursday afternoon after the irrigation engineers of Andhra Pradesh unilaterally started releasing water to the right canal (NSJC), though no decision was taken on water release at the November 23 three-member committee meeting of the Krishna River Management Board (KRMB), despite the opposition from the Telangana authorities citing lack of approval from the board.
The A.P. engineers did not heed to their Telangana counterparts’ pleas asking not to release water till a decision in the river board meeting, and continued water release. Telangana engineers followed suit and started water release to the left canal (NSLC) an hour later.
Water release from the reservoir unilaterally is set to deplete the water level and storage further and reduce the availability during the critical summer season extending into the next monsoon season, till the arrival of fresh flood. The fresh incident adds to the unease already prevailing between the two States following A.P. taking up a tunnel project from Nagarajunasagar reservoir to draw water for Palnadu water grid with gravity and without approval of the river board and consent of Telangana.
Sources in the Telangana Irrigation department stated that the A.P. irrigation authorities had started drawing water in the guise of meeting drinking water needs. They were planning to increase the drawl to 15,000 cusecs.
As per the joint projects’ management protocol issued by the KRMB, the Nagarajunasagar project is mandated to be operated, including taking care of its maintenance works by the Telangana Irrigation department and that of Srisailam by A.P. Water Resources department. However, A.P. has been repeatedly operating the right canal unilaterally.
According the Nagarjunasagar engineers, water release to the right canal was increased to 6,395 cusecs by A.P. engineers till 6 p.m. and the Telangana engineers gradually increased water release to the left canal to 5,580 cusecs.