business

GRIDCo restores power to parts of Ashanti and Western regions after chainsaw operators damage transmission line

GRIDCo restores power to parts of Ashanti and Western regions after chainsaw operators damage transmission line

The Ghana Grid Company (GRIDCo) has successfully restored the damaged 330kV Aboadze–Anwomaso transmission line, which tripped and caused power outages in parts of the Ashanti and Western Regions after illegal chainsaw operators felled a tree onto it. According to a press statement issued by GRIDCo, the incident occurred on Wednesday, November 25, 2026, when a large tree was felled onto a section of the transmission line between Tower 268 and Tower 269.

The Ghana Grid Company (GRIDCo) has successfully restored the damaged 330kV Aboadze–Anwomaso transmission line, which tripped and caused power outages in parts of the Ashanti and Western Regions after illegal chainsaw operators felled a tree onto it.

According to a press statement issued by GRIDCo, the incident occurred on Wednesday, November 25, 2026, when a large tree was felled onto a section of the transmission line between Tower 268 and Tower 269.

The damage forced system operators to reduce power supply to parts of Kumasi due to the unavailability of the critical line.

Following the trip, GRIDCo engineers undertook investigations and carefully patrolled the affected section to ascertain the cause of the incident. The necessary repair works were subsequently completed on Thursday, November 26, 2026, around 12:07 p.m., fully restoring the line to operation.

GRIDCo has since appealed to the general public to help protect critical electricity transmission infrastructure by refraining from illegal chainsaw operations and other activities in the vicinity of transmission lines and associated facilities.

The company expressed appreciation to all affected consumers for their patience, cooperation, and understanding during the period of the outage.

The incident highlights the severe damage and operational impact that illegal chainsaw actions have on the company's assets and its ability to transmit power reliably across the country.

  • line
  • gridco
  • transmission
  • power
  • ashanti
  • chainsaw
  • damage
  • part

Summaries and tags are generated automatically. Stay informed with VidiaNews.

Related news

ECG attributes Accra power outages to transformer upgrades and emergency faults
business

ECG attributes Accra power outages to transformer upgrades and emergency faults

The Electricity Company of Ghana (ECG) has blamed recent power outages in parts of Accra on transformer upgrades, replacement works and emergency faults on its distribution network. ECG’s General Manager in Charge of External Communications, Dr Charles Nii Ayiku Ayiku, said the company was undertaking transformer upgrades and replacements in parts of Accra East and Accra West to improve power supply.

Read →
ECG explains power outage affecting Tema, Afienya and surrounding communities
business

ECG explains power outage affecting Tema, Afienya and surrounding communities

The Electricity Company of Ghana (ECG) has attributed a power outage affecting several communities in the Tema Region to a fault in its distribution network, assuring affected customers that engineers are working to restore electricity supply. The outage has disrupted electricity supply to a number of residential, commercial and institutional areas, including Tema International School, Don Bosco, EU China Mall, Tulaku, Bethlehem, Sebrepor, Kakasunaka No. 2 and White Estates.

Read →