The Executive Director of the Institute of Energy Policies and Research, Kwadwo Poku, has accused the Finance Minister, Dr Cassiel Ato Forson, of delaying the release of funds needed to improve Ghana’s electricity transmission infrastructure. Speaking on JoyNews’ Newsfile on Saturday, November 28, 2026, Mr Poku said the funding was intended to support transmission interventions by the Ghana Grid Company (GRIDCo), including the development of the Takoradi-Kasoa 161kV transmission line.

The Executive Director of the Institute of Energy Policies and Research, Kwadwo Poku, has accused the Finance Minister, Dr Cassiel Ato Forson, of delaying the release of funds needed to improve Ghana's electricity transmission infrastructure.

He says the delay in securing financial authorisation for a US$50 million component of a US$250 million World Bank facility is affecting efforts to strengthen the national grid and address persistent power outages.

Speaking on JoyNews' Newsfile on Saturday, November 28, 2026, Mr Poku said the funding was intended to support transmission interventions by the Ghana Grid Company (GRIDCo), including the development of the Takoradi-Kasoa 161kV transmission line.

He explained that the US$50 million allocation was tied to specific performance conditions under a results-based financing arrangement, meaning GRIDCo had to meet certain requirements before the World Bank could release the funds.

Mr Poku said one of the requirements was for GRIDCo to develop and submit a methodology for implementing security-constrained economic dispatch to the Energy Commission.

However, he cited the World Bank document as indicating that GRIDCo had not completed the methodology or procured the necessary consultants.

He said the report also identified the absence of commitment authorisation from the Ministry of Finance as a factor preventing progress towards meeting the required targets.

“Actual current, it says that GRIDCo is yet to prepare the methodology and yet to procure the consultants, no commitment authorisation from the Ministry of Finance to allow for the disbursement needed to facilitate the achievement of this target,” he stated.

Mr Poku questioned why the government had not prioritised the release of the funds for transmission infrastructure while pursuing plans to expand electricity generation capacity.

“The Finance Minister, who wants to build a 1,450 megawatt plant in the Central Region, has not made sure that the money, 50 million dollars, for GRIDCo to achieve this, for that money to be released to build the Takoradi-Kasoa 161 KV line,” he said.

He warned that the planned expansion of generation capacity could face challenges if the transmission infrastructure required to evacuate the additional electricity was not upgraded.

According to him, the existing transmission corridor in the Central Region is ageing and may not have the capacity to transport the additional power to areas of demand.

“The central corridor line was built in 1960. Most of the fittings are rusted,” he said.

Mr Poku argued that increasing generation capacity without corresponding investment in transmission would not adequately address Ghana's electricity supply challenges.

He maintained that the country needed to strengthen its transmission network to ensure that electricity generated could be transported reliably to consumers.

  • transmission
  • gridco
  • finance
  • ministry
  • energy
  • poku
  • electricity
  • delay

Summaries and tags are generated automatically. Stay informed with VidiaNews.

Related news

Transmission gaps driving power outages despite improved generation – Energy analyst
business

Transmission gaps driving power outages despite improved generation – Energy analyst

The Executive Director of the Institute of Energy Policies and Research, Kwadwo Poku, has blamed persistent power outages in parts of the country on inadequate investment in electricity transmission infrastructure. Mr Poku said the country’s electricity sector required a comprehensive approach that addressed generation, transmission and distribution rather than concentrating resources on one component.

Read →
Mahama government cancelled KfW financing for Accra-Kumasi transmission line – Kwadwo Poku
politics

Mahama government cancelled KfW financing for Accra-Kumasi transmission line – Kwadwo Poku

The Executive Director of the Institute of Energy Policies and Research, Kwadwo Poku, has accused the Mahama administration of cancelling a financing arrangement with the German development bank KfW for a major electricity transmission project linking Accra and Kumasi. The proposed Accra-Kumasi transmission project was intended to reinforce electricity transmission capacity between Greater Accra and the Ashanti, Bono, Bono East, Ahafo and Northern regions.

Read →
Ghana’s power challenges could persist for two more years – Energy Analyst
business

Ghana’s power challenges could persist for two more years – Energy Analyst

Energy Analyst Kwadwo Poku has warned that Ghana’s current power challenges could persist for at least two years, blaming inadequate investment in electricity transmission infrastructure over the past two years. Mr Poku also questioned the government’s decision to cancel an agreement with German development bank KfW, as well as the delay in acting on a 50 million World Bank funding arrangement intended for the transmission sector.

Read →
Energy Ministry blames recent power outages on transmission and distribution infrastructure
business

Energy Ministry blames recent power outages on transmission and distribution infrastructure

The Director of Communications and Spokesperson for the Ministry, Richmond Rockson, said inadequate investments in the transmission sector over the years had left parts of the country’s electricity network struggling to meet growing demand. Mr Rockson said government was undertaking upgrades to the K1 and K2 transmission lines in Kumasi to significantly increase their capacity and improve reliability.

Read →
Dansoman, Adenta, Amasaman among power outage hotspots – Energy Ministry
politics

Dansoman, Adenta, Amasaman among power outage hotspots – Energy Ministry

The Ministry of Energy has identified Dansoman, Adenta, Amahia, parts of Oyarifa, Pokuase, Amasaman and Lakeside as areas experiencing persistent electricity supply challenges in recent weeks. Director of Communications and Spokesperson for the Ministry, Richmond Rockson, described the areas as power outage hotspots during an interview on JoyNews’ Newsfile on Saturday, November 28.

Read →
Lands Ministry, Newmont set up working group to strengthen the mining partnership
business

Lands Ministry, Newmont set up working group to strengthen the mining partnership

Emmanuel Armah-Kofi Buah has inaugurated a six-month Joint Ghana–Newmont Working Group to address concerns relating to the fiscal, regulatory and operational environment affecting the mining company’s investments in the country. The Committee includes representatives from the Ministry of Lands and Natural Resources, Minerals Commission, Ministry of Finance, Attorney-General’s Department, Ghana Revenue Authority and Environmental Protection Authority, alongside Newmont representatives.

Read →