business

GRIDCo completes 70% of Anwomaso–Ahodwo line upgrade; planned outages to begin Friday

GRIDCo completes 70% of Anwomaso–Ahodwo line upgrade; planned outages to begin Friday

The Ghana Grid Company Limited (GRIDCo) has completed 70% of the upgrade of the 161kV Anwomaso–Ahodwo transmission line in Kumasi, with planned power interruptions expected in some communities as engineers work to finish the remaining tasks. GRIDCo and the Electricity Company of Ghana (ECG) say the outstanding work involves stringing conductors on transmission towers.

The Ghana Grid Company Limited (GRIDCo) has completed 70% of the upgrade of the 161kV Anwomaso–Ahodwo transmission line in Kumasi, with planned power interruptions expected in some communities as engineers work to finish the remaining tasks.

The project, which is expected to be completed by the end of November 2026, is aimed at improving electricity supply reliability in Kumasi and surrounding communities.

GRIDCo and the Electricity Company of Ghana (ECG) say the outstanding work involves stringing conductors on transmission towers. The two companies say temporary outages are necessary to enable engineers to carry out the work safely and complete the project.

The planned interruptions will run from Friday, October 30, to Sunday, November 29, excluding weekends. Power will be interrupted between 9am and 5pm on days when work is being undertaken along the affected sections of the transmission line.

ECG is expected to publish a detailed schedule to inform customers in the affected communities about the specific dates of the outages.

In a joint statement issued in Tema on October 29, the two power companies said the temporary interruptions were necessary to protect engineers, other personnel and the public during the remaining works.

“While the temporary interruptions are necessary to ensure the safety of personnel and the successful completion of the works, the project represents an important investment in strengthening the transmission network and improving the reliability of electricity supply in the Ashanti Region,” the statement said.

GRIDCo and ECG appealed to residents and other electricity consumers in the affected areas to exercise patience and cooperate with the teams carrying out the upgrade.

“We appeal to the public, particularly affected communities, for your patience, understanding, and cooperation throughout this period,” the companies said, apologising for the inconvenience and assuring the public of their commitment to completing the project safely and on schedule.

  • gridco
  • line
  • upgrade
  • company
  • work
  • anwomaso
  • ahodwo
  • transmission

Summaries and tags are generated automatically. Stay informed with VidiaNews.

Related news

Ghana Bauxite Company secures US$250m Ecobank Financing to improve operations ahead of refinery
business

Ghana Bauxite Company secures US$250m Ecobank Financing to improve operations ahead of refinery

Ghana Bauxite Company Limited (GBC) has signed a US$250 million financing arrangement with Ecobank Ghana PLC to prepare and expand its Awaso mine to feed its planned alumina refinery. GBC Director, Robert Danso Boakye, disclosed this in an interview following the signing of the mandate that appoints Ecobank Ghana PLC as exclusive Mandated Arranger, on a best-efforts basis, for facilities of up to US$250 million.

Read →
BUA Cement donates ₦12m to families of eight Sokoto crash victims
business

BUA Cement donates ₦12m to families of eight Sokoto crash victims

By Musa Ubandawaki, Sokoto BUA Cement has donated ₦12 million to the families of eight people killed in a road accident along the Kajiji–Tambuwal road in Sokoto State. The company’s management visited the affected families in Tambuwal to deliver the assistance, accompanied by the District Head of Tambuwal, Alhaji Ahmad Dahiru, and the Chairman of Tambuwal Local Government Area, Hon.

Read →
EPA gave Empire Cement three months to plan relocation in 2023 – Former EPA Boss
business

EPA gave Empire Cement three months to plan relocation in 2023 – Former EPA Boss

Former Environmental Protection Authority (EPA) Executive Director Dr Henry Kwabena Kokofu says Empire Cement Ghana Limited was given three months in 2023 to prepare a plan to relocate its factory after regulators raised concerns about its location near the Densu Delta Ramsar Site. Dr Kokofu made the disclosure on the Citi Breakfast Show on Thursday, October 29, amid renewed regulatory action against Empire Cement’s operations near the Densu Delta Ramsar Site.

Read →
EPA gives Empire Cement 30 days to submit relocation plan
business

EPA gives Empire Cement 30 days to submit relocation plan

The Environmental Protection Authority (EPA) has given Empire Cement Ghana Limited 30 days to submit a comprehensive plan to relocate its cement grinding and bagging facility away from the Densu Delta Ramsar Site. The directive, signed by the EPA’s Chief Executive Officer, Professor Nana Ama Browne Klutse, follows years of regulatory concerns over the facility’s location, including its proximity to residential communities, Panbros Salt Industries Limited and the environmentally sensitive Densu Delta Ramsar Site.

Read →